Sunday, September 22, 2013

Timeline of Pilot Study

Date
Task 
July 30, 2013
IRB Submission
no later than
September 21, 2013
Second IRB Resubmission with requested changes
TBD
October X, 2013
IRB Approval
September 20, 2013 until IRB approval
Compile an email list of high school mathematics teachers in preparation for administering the survey
October X, 2013 (upon IRB approval)
Administer Survey Solicitation E-mail
October X, 2013 (upon IRB approval) - November 1, 2013
Survey Administration and Data Collection
November 1 - 8, 2013
Data Analysis
November 9 - 17, 2013
Write up findings and conclusions
November 18 - 22, 2013
Edit Paper
December 2, 2013
Stakeholder Presentation
December 4, 2013
UWG Presentation
December 7, 2013
Final Submission